Health authority has no objection to incinerator
In a letter, seen by the Irish Examiner, the HSA informs the planning board that Indaver has provided sufficient information on “consequence and risk assessment” to allow it to “not advise against the granting of planning permission in the context of major accident hazards”. The HSA is due to give evidence to An Bord Pleanála today at the ongoing oral hearing into the development.
The planned €140m waste-to-energy plant is earmarked a Seveso industry as it is a high-risk chemical site which handles specific chemicals or substances, such as methanol, which if not handled properly could give rise to a major accident. Under Seveso regulations, the HSA must give land use advice to the planning authority so public risk is minimised. There are 90 Seveso sites in Ireland and the Indaver site is deemed a lower-risk Seveso site.