Páirc Uí Chaoimh's reconstruction to cost €10m more than County Board expected
The revised cost of Páirc Uí Chaoimh’s reconstruction has been estimated at €95.8million, which includes required work on the playing surface.
As it was also confirmed all of Cork’s remaining Allianz League fixtures will be moved to Páirc Uí Rinn, the figure is almost €10m more than had been expected by the Cork County Board and €14.2m less than the worst case scenario set out by GAA stadium and commercial director Peter McKenna in The Irish Examiner in December.