Cost of Glanmire's delayed traffic and infrastructure project triples

A report published by the Comptroller and Auditor General said that the cost of building and construction materials increased by 40% between June 2017 and June 2024
Cost of Glanmire's delayed traffic and infrastructure project triples

Glanmire's infrastructure package will not be completed until the second quarter of 2026. File picture: Larry Cummins

A transport and road improvement package to accompany housing developments in Glanmire is running five years later than planned and is set to cost three times what was initially expected.

The project was set to run in tandem with 300 housing units but will now service 408 units which were delivered in the area by the end of last year. 

Already a subscriber? Sign in

You have reached your article limit.

Unlimited access. Half the price.

Annual €120 €60

Best value

Monthly €10€5 / month

More in this section

Lunchtime News

Newsletter

Keep up with stories of the day with our lunchtime news wrap and important breaking news alerts.

Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited