Construction company building hundreds of social housing units goes into examinership

Blacklough Construction, which is currently working on developments for Respond Housing Association, is insolvent on a cash-flow basis and unable to pay its debts, court heard
Firm's difficulties have largely been caused by the unprecedented 33% rise in the cost of building materials the industry has experienced since 2020, court told.

Firm's difficulties have largely been caused by the unprecedented 33% rise in the cost of building materials the industry has experienced since 2020, court told.

An interim examiner has been appointed by the High Court to a construction company that is currently building over 360 social housing units at five different sites in Ireland.

Blacklough Construction Limited sought the protection of the courts from its creditors as it is insolvent on a cash-flow basis and unable to pay its debts.

Blacklough is currently working on developments for the Respond Housing Association in Carrickmines, Co Dublin, Channel College, Malahide Road, in Dublin, Athboy Road, Navan, Co Meath, Charlestown, Mullingar, Co Westmeath, and Dundalk, Co Louth.

The court heard despite its current predicament, an independent experts report has stated the company has a reasonable prospect of survival if certain steps are taken, including the appointment of an examiner who would seek to agree a survival plan with the firm's creditors.

Rise in building materials costs

Counsel for Blacklough, Ross Gorman Bl said the firm's difficulties have largely been caused by the unprecedented 33% rise in the cost of building materials the industry has experienced since 2020.

In addition, a potential problem regarding planning permission has arisen regarding the development the firm is working on in Carrickmines, counsel added.

At the High Court on Thursday, Mr Justice Michael Quinn said he was satisfied to appoint chartered accountant and insolvency expert Joe Walsh as interim examiner to the company.

The company has 48 employees and also engages the services of subcontractors.

The company petitioned the court to appoint an examiner, who they claim can put together a scheme of arrangement with the company's creditors, which if approved by the court would help the firm survive.

The company has a registered address at Rathcoole, Co Dublin, and its sole director is Tara King from Naas, Co Kildare.

Her father, Gerard Walsh, is the company secretary and has extensive experience in the construction industry.

The court also heard the examiner will also deal with the company's employees, subcontractors and its trade creditors, whom the court heard are owed over €3m.

Independent expert's report

Independent expert Cormac Mohan had stated in his report on the firm that the creditors would do better in a successful examinership compared to if the company went into liquidation.

Seeking the appointment of an examiner, Mr Gorman said the company was set up in 2010, has been successful at building residential units, and had been profitable until quite recently.

The company was currently building 363 units on five different sites which were the subject of fixed price contracts.

The total contract price of the five sites Blacklough is currently working on is €65m, and to date the company has completed works to the value of €31m.

The significant rise in raw material for the construction sectors had resulted in the company sustaining loses, counsel said.

It was estimated the rise in costs, due to factors including Covid-19, Brexit and the war in Ukraine, meant the company has this year sustained approximate losses of €1.7m, counsel said.

Counsel said the firm's main client had agreed to a price increase, however, the monies it received were not sufficient to address all of Blacklough's losses.

It is building the units for the housing association Respond, who are supportive of the examinership application, counsel said.

Issue at Carrickmines site

Counsel said there was an additional issue at the Carrickmines site, where he said some 48 apartments have been built to roof level.

However, counsel said the entity that had engaged Blacklough to carry out the works had been informed by Dún Laoghaire Rathdown County Council that there was "a significant difficulty" with the site, regarding the precise location where the new properties have been built.

There was a question over whether the location of the new development complies with the planning permission granted for the site.

Counsel said Blacklough had informed its insurer about that matter.

Due to its financial situation, counsel said his client had "skeleton crews" on the sites.

Suppliers and creditors had also been making demands for payment, counsel added.

Counsel said putting the company into examinership would help to bring about a resolution of this situation, as well as seek to secure new investment.

Counsel said a party was interested in investing in the company.

Mr Justice Quinn said he was satisfied to appoint Mr Walsh as interim examiner, He directed the firm's creditors be put on notice of the application and adjourned the proceedings to a date later this month.

x

More in this section

Lunchtime News

Newsletter

Get a lunch briefing straight to your inbox at noon daily. Also be the first to know with our occasional Breaking News emails.

Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited