High Court retains stay on Pairc Uí Chaoimh contract ruling

The 45,000-seat stadium at Ballintemple was re-opened in 2017 following a two-year redevelopment. Photo: Diarmuid Greene/Sportsfile
The High Court has refused to lift a stay on a construction industry adjudicator dealing with a claim by a contractor for a further €1m payment for electrical works carried out in the revamp of Páirc Uí Chaoimh in Cork.
Last month, the court gave permission to Cork GAA to challenge the decision to refer the additional claim from OCS One Complete Solution to an adjudicator who had to give his decision - which was enforceable in law - by November 30.