‘Unauthorised’ wind farm told to cease operations

File photo

A wind farm which was not built according to planning permission has been issued with an enforcement notice to cease operations.

Barnafaddock Wind Farm in Ballyduff Upper, Co Waterford, was built using turbine 103m-diameter blades. It had permission for 90m-diameter blades.

Last November, An Bord Pleanála ruled that the wind farm constituted an unauthorised development because of the anomaly.

On March 22, Waterford City and County Council issued the enforcement notice which gives the owner of the wind farm six months to conform with the original planning permission.

This would require replacing the bigger blades, but it is unclear if such an operation could be undertaken without also dismantling the turbines. The unauthorised blades were affixed to eight of the 11 turbines on the farm, which began operating in 2015.

The company behind the farm, Barnafaddock Sustainable Electricity Ltd, has applied for substitute consent, a form of retention planning permission for projects that involve an environmental impact study.

The longer blades were installed after the developer received a “letter of comfort” from the planning department in 2013 to go ahead even though it was in contravention of the planning permission.

In the event of the wind farm having to cease operations, the local authority could be open to legal action on the basis of assurances given during construction.

A spokesperson for the local authority told the Irish Examiner that no issues arise in relation to health, safety, or insurance while the wind farm continues to operate as an unauthorised development.

The longer blades were brought to the attention of the local authority by residents who investigated the issue as a result of what they considered excessive noise pollution.

One resident, Sean Harris, accused the council of dragging its heels.

A spokesperson for Waterford City and County Council said the local authority will not take any enforcement action before a decision by the planning board on the substitute consent.

Attempts to contact Blackrock, the current owner of Barnafaddock Sustainable Electricity, were unsuccessful.

More on this topic

Cast for 25th James Bond film to be announced

Time 'want away' stars acknowledged their role in failure

The new tour that brings you behind the scenes at the Everyman Theatre

Kerry teenager dies after quad bike accident

More in this Section

Fire safety issues at older people's residential centres

HSE failing both living and dead in South East, says health group

Twitter suspends account of dissident republican group Saoradh

Over €700k worth of cocaine and cannabis seized in Dublin


Lifestyle

On the 6th anniversary of the Rana Plaza tragedy – how transparent are fashion brands being now?

How to make Henry Firth and Ian Theasby’s New York-style baked strawberry cheesecake

Want to cut down on sugar? Experts reveal how to slash your intake in 6 simple steps

As Taylor Swift goes all Victoriana at the Time Gala – 3 times she’s made a splash on the red carpet

More From The Irish Examiner