Cost of Glanmire's delayed traffic and infrastructure project triples

A report published by the Comptroller and Auditor General said that the cost of building and construction materials increased by 40% between June 2017 and June 2024
Glanmire's infrastructure package will not be completed until the second quarter of 2026. File picture: Larry Cummins

Glanmire's infrastructure package will not be completed until the second quarter of 2026. File picture: Larry Cummins

A transport and road improvement package to accompany housing developments in Glanmire is running five years later than planned and is set to cost three times what was initially expected.

The project was set to run in tandem with 300 housing units but will now service 408 units which were delivered in the area by the end of last year. 

You have reached your article limit. Already a subscriber? Sign in

Unlimited access starts here.

Try from only €0.25 a day.

Cancel anytime

More in this section

Lunchtime News

Newsletter

Get a lunch briefing straight to your inbox at noon daily. Also be the first to know with our occasional Breaking News emails.

Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited