'Absolutely reasonable' to expect competent builder to complete school in 22 weeks, court told

Education Minister talking action against Tyrone-based Western Building Systems over the alleged systemic defects in the construction of Ardgillan Community School in Balbriggan, Co Dublin
Tyrrelstown Educate Together School in Dublin:  Assistant secretary at the Department of Education Hubert Loftus told the High Court 'our worst fears' were realised after opening-up works were carried out after Ardgillan Community School in balbriggan was closed. File picture: Sam Boal/RollingNews.ie

Tyrrelstown Educate Together School in Dublin:  Assistant secretary at the Department of Education Hubert Loftus told the High Court 'our worst fears' were realised after opening-up works were carried out after Ardgillan Community School in balbriggan was closed. File picture: Sam Boal/RollingNews.ie

An assistant secretary at the Department of Education has told the High Court it was "absolutely reasonable" to expect a competent builder to complete a new school in 22 weeks under a rapid system-build process rather than by traditional methods, which can take more than three times longer.

Hubert Loftus, who has headed the department's planning and building unit since 2017, was giving evidence in the ongoing action by the Education Minister against Tyrone-based Western Building Systems over the alleged systemic defects in the construction of Ardgillan Community School in Balbriggan, Co Dublin.

The minister says remediation works will cost some €11.5m, whereas Western says it could have been done for as little as €1.2m if the works had been carried out expeditiously. It says the minister's claim is vastly exaggerated.

The court has been told, during the 10 days of the hearing via a hybrid Trialview video/physical courtroom before Mr Justice Brian O'Moore, that among the defects were failure to properly tie inner and outer walls, fire safety problems and electrical defects. Ardgillan itself had to be completely rewired, although it was only built in 2009.

Under cross examination on Wednesday by John Trainor SC, for Western, Mr Loftus was asked if the 22-week timeline for completing Ardgillan under the rapid design/build system was what would have been expected.

Mr Loftus replied that the timeline was expressed by experts, and from experience of other schools built under this system, it "was absolutely reasonable to expect a competent builder to achieve the standard required".

Mr Loftus earlier told the minister's counsel, David McGrath SC, that when the department first learned of the defects in Ardgillan, the reaction was one of “shock, horror and dismay that a company could have built a school which had such defects hidden away in the bowels of the building and covered them up until we could open them up".

Crisis management mode

He said when the defects were discovered, Ardgillen was closed down. The department went immediately into crisis management mode because it was an unprecedented situation in terms of issues and scale being faced, he said.

Given that Western had built 39 other schools, it was with "a sense of dread" that Mr Loftus himself and others went out to another school in Tyrrelstown, Dublin, when opening up works were carried out after the Ardgillan inspection had taken place.

He felt it was important for him to be there on that day and, when the opening up took place, "our worst fears" were realised. That school closed early for the term and an inspection programme in the other Western-built schools began.

What was found was "a mountain to climb and it was an "Everest in terms of what we were facing". The crisis management unit relocated to Tullamore and daily press releases were issued aimed at the various school communities as there were concerns about whether it was safe to keep the schools open.

Mr Loftus said there were some 16,500 pupils attending 46 schools surveyed, including non-Western schools.

In Mr Trainor's earlier cross examination of Mr Loftus, counsel asked if his "strong and understandable reaction" to the discovery of the defects meant he believed that there was a deliberate or reckless decision to leave such defects.

Mr Loftus said he supposed it was hard to know but in circumstances where they were continually going into school buildings and "finding surprises, none of which are pleasant", it was not what one would expect from a competent builder.

He also said Western did not meet its contractual responsibilities and it was clear to him when the defects were discovered and it was also clear "as I sit in the witness box today".

Asked if, in conversations he had with Western's founder Martin McCloskey, he held the view that Western was solely responsible for all the problems, Mr Loftus said his conversations with Mr McClosely were "quite limited".

He said Western had not been forthcoming in supplying information about the builds, which would have helped "us understand what was before us in 2019". The department's experts had to effectively "reverse engineer" the buildings because what was found during opening up the structures did not correspond with the built-drawings.

He also told the court the first time Western accepted any responsibility was effectively "on the steps of the court" last September.

The hearing continues.

More in this section

Lunchtime News

Newsletter

Get a lunch briefing straight to your inbox at noon daily. Also be the first to know with our occasional Breaking News emails.

Cookie Policy Privacy Policy Brand Safety FAQ Help Contact Us Terms and Conditions

© Examiner Echo Group Limited