BAM's claims on National Children's Hospital 'not credible', says minister

The under-construction National Childrenâs Hospital in Dublin Picture: Brian Lawless/PA
The Health Minister has described claims by BAM that large sections of the new National Childrenâs Hospital are complete as ânot credibleâ, as doubts remain over when the facility will open.
Jennifer Carroll MacNeill has strongly criticised the developer, saying that only around 800 rooms within the hospital are completed to standard.
In a statement on Wednesday evening, Ms Carroll MacNeill said many rooms offered up by BAM have âopen snagsâ and are âchequerboarded throughout the hospitalâ.
Ms Carroll MacNeill said this means they have not been offered up in large sections, but rather on a room-by-room basis in different parts of the hospital.
âWhat is needed is whole zones or blocks of rooms, from the ground floor up to the sixth floor in order to gain and benefit from meaningful additional early access for Childrenâs Health Ireland.
âBAMâs suggestion that ongoing design changes are impacting the completion of the hospital is not credible, especially given the fact that BAM is claiming that the project is 99% complete. It is BAMâs responsibility to get its final 1% done.â Ms Carroll MacNeill called for the developer to provide âthe resources necessaryâ to complete the projectâ and ensure it is handed over in a timely manner.
The row began early on Wednesday, after the Minister cast doubt on the completion timeline of the hospital, laying the blame on BAM.
She highlighted the number of contractors on site had fallen by half compared to late 2024.
âIt was 800 to 900 contractors routinely on site every week at the end of 2024; thereâs now 400 to 500,â Ms Carroll MacNeill said.
Ms Carroll MacNeill also alleged the developer was not using its entire provisioned budget, saying between âŹ2.8m and âŹ3m was being drawn down each month, of an allocated âŹ10m.
However, BAM rejected Ms Carroll MacNeillâs assertions, saying they were âdisappointedâ by comments.
âHer remarks indicate she has only received partial information in relation to the current status of the National Childrenâs Hospital Ireland project,â BAM said.
âThe project is more than 99% complete. Due to the specialist nature of the commissioning work currently underway at this late stage, it is entirely normal that there are fewer personnel on site compared to this time last year.âÂ
On the drawdown of funds, the contractor referred to a previous meeting with then-minister Stephen Donnelly, where a commitment was made that there would be no further design changes.
However, BAM says there have since been 84 new and revised design changes.
âThe majority of the remaining work on the project relates to these changes, for which BAM has not received payment,â the spokesperson said.
âAs a result, BAM has been obliged to initiate the contractâs dispute resolution mechanism to secure appropriate compensation.â Both Ms Carroll MacNeill and the National Paediatric Hospital Development Board have rejected BAMâs assertions that design changes are responsible for delays.
âThis [design change requests] equates to less than 4% of the 5,762 rooms within the hospital. It is not credible to state that this is the reason for BAMâs lack of progress,â the NPHDB said.
The spokesperson said BAM remain behind on all key performance indicators tracked by the NPHDB.