Challenge over €65m Kerry road plan fails

An Taisce has lost its High Court legal challenge to planning approval for a €65m road-widening scheme on the N86 between Tralee and Dingle.

A 28km project between Dingle and Annascaul, involving straightening and widening of the road, was on hold pending the outcome of the Commercial Court case. Part of the scheme east of Annascaul is finished.

An Taisce sought orders quashing a November 2014 decision of An Bord Pleanála granting approval for the scheme, proposed by Kerry County Council, to improve the road between Dingle and Annascaul and between Gortbreagoge and Camp Rd. The council planned to include a cycleway on each side of the road, plus a hard margin.

The board previously re-fused permission for the scheme but, after that decision was overturned by the High Court in 2013 on grounds including failure by the board to adequately consider cyclists and pedestrians, the board reconsidered and approved the scheme in November 2014.

In proceedings initiated earlier this year, An Taisce claimed the overall road project was not adequately assessed in accordance with the provisions of the Environmental Impact Assessment (EIA) directive.

The road project is significant in scale and the Dingle peninsula has a high concentration of cultural heritage, it argued.

In his judgment, Mr Justice Robert Haughton said the essence of An Taisce’s claim was the 4.2km section of road between Annascaul and Gortbreagoge, along with the 28km scheme, constituted a single 32km “project” for the purpose of the directive. It claimed an Environmental Impact Statement (EIS) and EIA were required for the entire project and failure to include the 4.2km in an EIA amounted to unlawful “project-splitting” in breach of the directive.

Because the validity of Kerry County Council’s decision to grant permission for the 4.2km scheme was not directly challenged in this case, the council’s permission for that 4.2km scheme was “unimpeachable”, the judge ruled.

That meant the central issue was whether the board was entitled to approve the 28km scheme in the absence of an EIS or EIA of the entire 32km, the judge said.

He upheld arguments by the board that An Taisce, before it could allege unlawful “project-splitting”, should have challenged a November 16, 2011, direction of the board requiring the council to prepare an EIS for the 28km scheme. The eight-week limit for such judicial review challenges ran from November 16, 2011, or, at the latest, December 21, 2011, the date of receipt of the EIS, he said.

The November 2014 decision could not be attacked without challenging the validity of the underlying 2011 direction, he found. The period for such a challenge had long expired, there was no application for an extension of time, and this case must be dismissed.

In the circumstances, it was not appropriate for the court to express a view on whether there was project-splitting contrary to EU or national law.


Lifestyle

Spring has sprung and a new Munster festival promises to celebrate its arrival with gusto, says Eve Kelliher.Spring has sprung: Munster festival promises to celebrate with gusto

The spotlight will fall on two Munster architects in a new showcase this year.Munster architects poised to build on their strengths

Prepare to fall for leather, whatever the weather, says Annmarie O'Connor.Trend of the week: It's always leather weather

The starting point for Michael West’s new play, in this joint production by Corn Exchange and the Abbey, is an alternative, though highly familiar, 1970s Ireland. You know, elections every few weeks, bad suits, wide ties, and a seedy nexus of politics and property development.Theatre Review: The Fall of the Second Republic at Abbey Theatre, Dublin

More From The Irish Examiner